Projects Delivered

FY 2010

  • Rampura Agucha Mine expansion from 5.00 million tonnes per annum to 6.00 million tonnes per annum, increasing the total ore production capacity of the Company to 8.60 million tonnes per annum.
  • Commissioned the 210,000 tonnes per annum Hydrometallurgical Zinc Smelter at Dariba Smelting Complex, increasing the Zinc & Lead metal production capacity to 964,000 tonnes per annum (879,000 tonnes of Zinc and 85,000 tonnes of Lead)

FY 2009

  • Rampura Agucha Mine expansion from 3.75 million tonnes per annum to 5.00 million tonnes per annum, increasing the total mining capacity of the Company to 7.40 million tonnes per annum
  • 88,000 tonnes per annum zinc debottlenecking completed at Chanderiya Smelting Complex & Debari Zinc Smelter making the total metal production capacity to 754,000 tonnes per annum
  • Commissioned 80 MW Captive Power Plant at Zawar Mines
  • Commissioned 34.4 MW Wind Energy Farms making the Company's total Wind Energy capacity to 123.2 MW.

FY 2008

  • Commissioned 170,000 tonnes per annum of Hydrometallurgical Zinc Smelter (Hydro II) in a benchmark time of 20 months at Chanderiya Smelting Complex
  • Commissioned 80 MW Captive Power Plant at Chanderiya Smelting Complex
  • 5,000 tonnes of zinc debottlenecking completed at Debari Zinc Smelter
  • Commissioned 50.4 MW of Wind Energy Farms at Gujarat

FY 2007

  • Sindesar Khurd Mine began production with an initial production capacity of 0.3 million tonnes per annum
  • Commissioned 38.4 MW of Wind Energy Farms at Gujarat

FY 2006

  • Commissioned 170,000 tonnes per annum of Hydrometallurgical Zinc Smelter (Hydro I) at Chanderiya Smelting Complex
  • Commissioned 2 X 77 MW Captive Power Plant at Chanderiya Smelting Complex
  • Commissioned 50,000 tonnes per annum of Ausmelt Lead Smelter at Chanderiya Smelting Complex

FY 2005

  • Rampura Agucha Mine expansion from 2.30 million tonnes per annum to 3.75 million tonnes per annum

FY 2004

  • 35,000 tonnes of zinc debottlenecking completed at Chanderiya Smelting Complex

FY 2003

  • 32,000 tonnes of zinc debottlenecking completed at Debari Zinc Smelter and Vizag Zinc Smelter
  • Debottlenecking of Rampura Agucha Mine from 1.37 million tonnes per annum to 2.30 million tonnes per annum

FY 1991

  • Commissioned 70,000 tonnes per annum of zinc and 35,000 tonnes per annum of lead Pyro metallurgical Lead-Zinc Smelter at Chanderiya
  • Rampura Agucha Mine began production with an initial production capacity of 0.9 million tonnes per annum